Sri Lanka to ration power in key towns and villages
08 Aug, 2012 23:56:12
Aug 08, 2012 (LBO) –Sri Lanka will cut power for two hours and fifteen minutes during the daytime Thursday (August 09) owing to a breakdown in a Chinese build coal plant in the north western region in the Island, the power ministry releasing a statement said.
Operations at Sri Lanka's newly build Lakvijaya coal power plant in north-western Puttalam district was temporarily halted this morning due to a problem in a transmission line, the ministry said.

The national grid has lost 300 megawatts of power since Wednesday morning due to the breakdown, the ministry statement said.

Power cuts will be imposed in 58 key towns and villages island-wide starting from 8.30 am in the morning on Thursday, the statement said.

Power cuts will be imposed in four time blocks to different parts of the island including the North and the East.

Kirillawela, Mahara, Kadawatha, Ganemulla, Gampaha, Biyagama, Galahitiyawa, Siyambalape, Paliyagoda, Maradana, Uswetakeiyawa, Kerawalapitiya, Katunayaka, Aandiambalama, Henatiyana, Kelaniya, Dalugama, Kosgama, Pugoda, Kirindiwela, Randawana, Malwana, Weyangoda, Nittambuwa, Pasyala, Athurugiriya, Kaduwela, Mulleriyawa, Angoda, Kosgama, Hanwella, Labugama, Pannipitiya, Siddamulla, Maththegoda and Kottawa areas in the western province will experience power cuts from 8.30 to 10.45 am, the power ministry said.

Some areas in northern and southern zones in the western province will not have power from 10.45 to 1.00pm including Sapugaskanda, Ragama, Nawagamuwa, Bulathsinhala, Bandaragama, Pamunugama, Maharagama, Dehiwala, Mount Lavinia, Panadura, Wadduwa, Kalutara and Piliyandala.

Power cuts will be imposed in Thalangama, Koswatta, Malabe, Athurugiriy, Arangala, Horana, Thalawathugoda, Depanama, Hokandara, Sri Jayawardenapura and Battaramulla during 1.00 to 3.15 pm.

From 3.15 to 5.30pm areas belonging to the southern zone of the western province will experience power cuts including Athurugiriya, Homagama, Horana, Pannipitiya, Battaramulla and Koswatta, the ministry schedule showed.

The power ministry didn’t specify whether the power cuts would continue beyond Thursday or whether it was only on Thursday.

Bookmark and Share
Your Comment
Your Name/Handle
Your Email (Your email will not be dispalyed)
Location
Country
Your Email
Receivers Email
Your Comment
 
READER COMMENT(S)
8. Lakshman Perera Aug 10
The times you have posted, no doubt given to you by some bureaucratic buffoon, are not what is happening. My power was cut today, Friday, before 8am and wasn't restored until afternoon.
7. kawdaboy Aug 10
@ I Bunkum Dirichcha Cheena Lanu!
6. Jack Point Aug 10
Would like to know the following: 1. How many days has the plant been out of commission due to breakdowns since it was completed? 2. What is the cost of generation per unit?
5. I Bunkum Aug 09
May I suggest Ministry suspends the name of the power plant "Lakvijaya", which means Sri Lankan victory until the issues a resolved so the plant can run few months without a breakdown. Temporarily, I suggest we rename the plant "Cheena Lanu"
4. tariq Aug 09
We the tax payers demand justice! Sack the people who are responsible for this blunder!
3. Concerneed Aug 09
The Wonder Of Asia? No the Laughing stock of Asia! Chinese built, 9% loan interest, and then binding deal for SL to buy coal only from China at the price they demand, great deal for China!All of this and it dont work......Do I send my fuel bill for generator to the minster?
2. kawdaboy Aug 09
Someone senior at the power ministry has to walk the plak.
1. Jack Point Aug 09
Always break down, no?