PUCSL says gaps in new CEB generation plan, 300MW LNG approved

power

Aug 08, 2016 (LBO) – Sri Lanka’s power regulator Public Utilities Commission (PUCSL) has not given the full nod for the Ceylon Electricity Board’s (CEB) base case generation plan saying it has not addressed all the original concerns raised, the Commission said in a letter to the CEB. “The Commission is of the view that the transmission licensee has not demonstrated the consideration of facts demand forecasting, DMS and related investment programmes, absorbing electricity from renewable sources, availability on Liquid Natural Gas as an alternative to coal fired plants, transmission system development cost minimization and alternative in case of Sampur delay,” the letter said. “In your submission the base case scenario was given without justification or data at the least cost scenario is not visible. Further the plan submitted for the period 2017-2036 was not the plan referred to in commission decision conveyed in December 18, 2015 letter to the CEB.” It says that the CEB has subjected the plan to government policy for which policy directives are awaited from the government. “Hence we can’t approve the plan in full.
buy clomid online buy clomid online no prescription
” The original plan was rejected on shortcoming in the demand forecasting methodologies where CEB may have erred in over-forecasting demand but given frequent delays. However, as an emergency measure the commission says that it will approve a 300 MegaWatt LNG combined cycle plant in the Western province. "Considering the gravity of the power situation in 2017-2020 period, the Commission would consider power plants identified for the period 2017-2020 in the LCLTGEP as an alternative to the delay in Sampur Coal Power Plant," the regulator letter went on to say. "Hence approval is granted to the Transmission Licensee to proceed with the procurement of power plants identified for the period 2017-2020 in the submissions made vide your letter dated July 27, 2016 as part of the LCL TGEP and any such procurement is to be carried out in compliance with the provisions of the SL Electricity Act." The PUCSL in 2015 warned that immediate action was necessary and that the CEB needs to expedite its submission of the Least Cost Long Term Generation Expansion Plan (LCLTGEP) 2015 – 2034 with the relevant changes. “You are required to submit the LCLTGEP 2015 -2034 on or before August 01, 2016,” the power regulator, PUCSL said in a letter dated December 2015 to the CEB. “The Commission has observed that under the drought conditions, even with planned plant additions, Sri Lanka is envisaged energy and capacity shortages in year 2018/19 and beyond and the transmission licensees delay in submission of the LCLTGEP 2015 – 2034 could further aggravate this situation.” As per CEB forecasts Sri lanka’s generation demand is expected to grow 5.5 percent per annum during 2015 – 2022 while in addition the peak demand is expected to grow at 4.4 percent per annum.
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Top
0
Would love your thoughts, please comment.x
()
x